Difference between revisions of "NSOC2022Ping"
From Nsnam
Chandrakant (Talk | contribs) (→Project Overview) |
Chandrakant (Talk | contribs) (→Weekly Reports) |
||
(14 intermediate revisions by 2 users not shown) | |||
Line 8: | Line 8: | ||
* '''Mentors:''' Tommaso Pecorella, Tom Henderson | * '''Mentors:''' Tommaso Pecorella, Tom Henderson | ||
* '''Project Goals:''' Create a new Ping application for ns-3, to replace the existing v4Ping and Ping6. | * '''Project Goals:''' Create a new Ping application for ns-3, to replace the existing v4Ping and Ping6. | ||
− | ** The two applications "V4Ping" and "Ping6" do their respective jobs, but they have | + | ** The two applications "V4Ping" and "Ping6" do their respective jobs, but they have some main issues: |
*** They have different parameters | *** They have different parameters | ||
*** There is a lot of code duplication | *** There is a lot of code duplication | ||
*** They have an output that is not consistent with the one you get in Linux | *** They have an output that is not consistent with the one you get in Linux | ||
− | * '''Repository:''' https://gitlab.com/ | + | * '''Repository:''' https://gitlab.com/tommypec/ns-3-dev-new-ping (branch 'nsoc-22') |
− | * '''About Me:''' I am currently a BCA Student (Bachelor's of Computer Application) at Utkal University, Bhubaneshwar, Odisha, India. I | + | * '''About Me:''' I am currently a BCA Student (Bachelor's of Computer Application) at Utkal University, Bhubaneshwar, Odisha, India. I am interested in Computer Networking and Problem-solving. I have a huge interest in Opensource software development, I was excited to open source in my 6th Grade when I first used the vlc media player. I started open source by participating in GCI, I contributed to CCEXTRACTOR but due to some academic commitments I was not able to complete it. I have developed several projects during my academics [https://www.linkedin.com/in/chandrakant-jena-5aab131a7/ (Linked In)] and Finally got a chance to develop some projects of my interest i.e '''Computer Networking'''. I Joined '''Ns-3''' in September 2021 because I developed some interest in computer Networking and always wanted to get some practical experience, Thanks to '''Ns-3'''. Apart from this, I am a sports lover, I used to play cricket and football which later refreshes my mind and help me to concentrate on my work. |
= Milestones and Deliverables = | = Milestones and Deliverables = | ||
+ | * [https://docs.google.com/document/d/1nApGYZOdvD6oXaSjmkGeZvYPfTaXhxT6HWHrretiXGI/edit?usp=sharing Detailed Project Plan and Approach] ( I will continuously update throughout the NSoC program duration) | ||
+ | |||
+ | = Weekly Reports = | ||
+ | |||
+ | '''Week 1''' | ||
+ | |||
+ | Duration: June 13 - June 19 | ||
+ | |||
+ | * Learned about the original Linux Ping Application working. | ||
+ | * visualized the attributes present in Linux Ping Application and relate to that of Ns-3 Ping Application. | ||
+ | * Discussed approach plans with mentors, attributes to be added, Functionality, and Expected output for the New Ping application. | ||
+ | |||
+ | '''Week 2''' (Taken Leave) | ||
+ | |||
+ | Duration: June 20 - July 5 | ||
+ | |||
+ | * I have Taken leave because of my Entrance Examination on 5 July. Does not contribute much to the project. | ||
+ | |||
+ | '''Week 3''' | ||
+ | |||
+ | Duration July 6 - July 11 | ||
+ | |||
+ | * Added initial code to bring support for IPv4 in the Ping Application [https://gitlab.com/tommypec/ns-3-dev-new-ping/-/commit/731ac17b86f7c9168aed7d5350e0f722bf278e12 commit]. | ||
+ | * Discussed with mentors to develop the Ping example. | ||
+ | |||
+ | '''Week 4''' | ||
+ | |||
+ | Duration July 12 - July 17 | ||
+ | * Developed Ping example but it had some issues while building the topology. | ||
+ | * Learned to use Ns-3 Debugger to debug source code. | ||
+ | |||
+ | '''Week 5''' | ||
+ | |||
+ | Duration July 18 - July 23 | ||
+ | * Ping-example have been developed successfully. | ||
+ | * Developed count feature for the new ping application. | ||
+ | |||
+ | '''Week 6''' | ||
+ | |||
+ | Duration July 24 - July 29 | ||
+ | * Discussed plans and approach for adding the Interface Address feature. | ||
+ | * Didn't add much code due to my semester exam. | ||
+ | |||
+ | '''Week 7''' | ||
+ | |||
+ | Duration July 30 - August 4 | ||
+ | * Added two new features Interface_address and destination address to the new Ping Application. | ||
+ | * Destination feature had some bugs and I fixed them. | ||
+ | * Added Count test case for IPv4 and IPv6. | ||
+ | |||
+ | '''Week 8''' | ||
+ | |||
+ | Duration August 5 - August 10 | ||
+ | * Enable IPv6 in Ping. | ||
+ | * Improved IPv6 testcase and finish initial IPv6 implementation and test. | ||
+ | * Add Testcase for Count, interpacket-interval and size. | ||
+ | |||
+ | '''Week 9''' | ||
+ | |||
+ | Duration August 11 - August 16 | ||
+ | * Added traces for sending pings | ||
+ | * Added count trace in test and improve test cases for ping application. | ||
+ | |||
+ | '''August 17 - August 25''' | ||
+ | |||
+ | Planned for the next implementation to be added, didn't added much code just added initials for timeout attribute. |
Latest revision as of 07:23, 1 September 2022
Back to NSoC 2022 projects
Project Overview
- Project Name: Ping and Ping6 Enhancements in ns-3
- Student: Chandrakant Jena
- Mentors: Tommaso Pecorella, Tom Henderson
- Project Goals: Create a new Ping application for ns-3, to replace the existing v4Ping and Ping6.
- The two applications "V4Ping" and "Ping6" do their respective jobs, but they have some main issues:
- They have different parameters
- There is a lot of code duplication
- They have an output that is not consistent with the one you get in Linux
- The two applications "V4Ping" and "Ping6" do their respective jobs, but they have some main issues:
- Repository: https://gitlab.com/tommypec/ns-3-dev-new-ping (branch 'nsoc-22')
- About Me: I am currently a BCA Student (Bachelor's of Computer Application) at Utkal University, Bhubaneshwar, Odisha, India. I am interested in Computer Networking and Problem-solving. I have a huge interest in Opensource software development, I was excited to open source in my 6th Grade when I first used the vlc media player. I started open source by participating in GCI, I contributed to CCEXTRACTOR but due to some academic commitments I was not able to complete it. I have developed several projects during my academics (Linked In) and Finally got a chance to develop some projects of my interest i.e Computer Networking. I Joined Ns-3 in September 2021 because I developed some interest in computer Networking and always wanted to get some practical experience, Thanks to Ns-3. Apart from this, I am a sports lover, I used to play cricket and football which later refreshes my mind and help me to concentrate on my work.
Milestones and Deliverables
- Detailed Project Plan and Approach ( I will continuously update throughout the NSoC program duration)
Weekly Reports
Week 1
Duration: June 13 - June 19
- Learned about the original Linux Ping Application working.
- visualized the attributes present in Linux Ping Application and relate to that of Ns-3 Ping Application.
- Discussed approach plans with mentors, attributes to be added, Functionality, and Expected output for the New Ping application.
Week 2 (Taken Leave)
Duration: June 20 - July 5
- I have Taken leave because of my Entrance Examination on 5 July. Does not contribute much to the project.
Week 3
Duration July 6 - July 11
- Added initial code to bring support for IPv4 in the Ping Application commit.
- Discussed with mentors to develop the Ping example.
Week 4
Duration July 12 - July 17
- Developed Ping example but it had some issues while building the topology.
- Learned to use Ns-3 Debugger to debug source code.
Week 5
Duration July 18 - July 23
- Ping-example have been developed successfully.
- Developed count feature for the new ping application.
Week 6
Duration July 24 - July 29
- Discussed plans and approach for adding the Interface Address feature.
- Didn't add much code due to my semester exam.
Week 7
Duration July 30 - August 4
- Added two new features Interface_address and destination address to the new Ping Application.
- Destination feature had some bugs and I fixed them.
- Added Count test case for IPv4 and IPv6.
Week 8
Duration August 5 - August 10
- Enable IPv6 in Ping.
- Improved IPv6 testcase and finish initial IPv6 implementation and test.
- Add Testcase for Count, interpacket-interval and size.
Week 9
Duration August 11 - August 16
- Added traces for sending pings
- Added count trace in test and improve test cases for ping application.
August 17 - August 25
Planned for the next implementation to be added, didn't added much code just added initials for timeout attribute.